Work is progressing well with the Parade Street sewer separation project and crews are now advancing beyond Willow Street toward Ryerson Court. Please be advised of the following:
➡ The intersection of First Street and Parade Street has been reopened
➡ Parade Street is now closed between First Street and Brunswick Street. This closure will be for approximately 6 weeks for Phase 2 of Sewer Separation Project.
We thank everyone affected for their patience and understanding as we continue to work on this important infrastructure upgrade.